Question: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 1 1 B A 1 2 C A 9 D B 5 E B 1 0 F

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 11
B A 12
C A 9
D B 5
E B 10
F D 9
G C, E 5
H F, G 10
I G, H 9
a. What is the early start date for activity H?
b. What is the late finish date for activity B?
c. Determine the minimum number of weeks for completing the project.