Question: Activity. Immediate Predecessor. Time (Weeks) A - 1 B A 5 C A 4 D C 2 E B, D 5 F E 2 G

Activity. Immediate Predecessor. Time (Weeks) A - 1 B A 5 C A 4 D C 2 E B, D 5 F E 2 G D 4 H F, G 3 1) Draw the critical path diagram, showing activity durations and precedence relationships. 2) What is the critical path? 3) How many weeks will it take to complete the project? 4) On your network diagram in question 1 above, show the early start, early finish, late start, and late finish times for each activity. 5) Which activities have slack, and how much? 6) Due to unavailable resources, Task G will be delayed by 2 weeks. Does this have an impact on the total time required to complete the project?