Question: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 1 1 B A 1 2 C A 9 D B 5 E B 1 0 F
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E B
F D
G C E
H F G
I G H
e What is the critical path? Enter the activities in capital letters with hyphens but no spaces separating the activities. For example, ACG
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
