Question: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 2 C A 5 D B 6 E C D 2 F D 3
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E C D
F D
G F
H E G
b What is the critical path?
multiple choice
ACEFGH
ACEH
ABDFGH
ACEGH