Question: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 2 C A 5 D B 6 E C D 2 F D 3

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 2
C A 5
D B 6
E C D 2
F D 3
G F 5
H E G 4
b. What is the critical path?
multiple choice 1
A-C-E-F-G-H
A-C-E-H
A-B-D-F-G-H
A-C-E-G-H