Question: Return to questionItem 4 Problem 5 - 8 ( Algo ) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A

Return to questionItem 4
Problem 5-8(Algo)
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 2
C A 5
D B 6
E C%media:cm.png% D 2
F D 3
G F 5
H E%media:cm.png% G 4