Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 2 C A 5 D B 6 E

Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 2
C A 5
D B 6
E C%media:cm.png% D 2
F D 3
G F 5
H E%media:cm.png% G 4
What is the critical path?
multiple choice 1
A-C-E-G-H
A-B-D-F-G-H
A-C-E-F-G-H
A-C-E-H
How many weeks will it take to complete the project?
Which activities have slack, and how much?
multiple choice 2
C9 weeks E6 weeks.
E1 week H4 weeks.
B1 week D3 weeks.