Question: Activity Immediate Predecessors Completion Time ( Weeks ) A N / A 2 B A 3 C A 4 D B 1 E B ,

Activity
Immediate
Predecessors
Completion
Time (Weeks)
A
N/A
2
B
A
3
C
A
4
D
B
1
E
B,C
5
F
D
6
G
E
2
H
E
3
Q5. What are the latest start and the latest finish of activity E?