Question: Activity Immediate Predecessor(s) Time (days) A - 7 B A 4 C A 6 D B 6 E B 4 F C 4 G D
Activity Immediate Predecessor(s) Time (days) A - 7 B A 4 C A 6 D B 6 E B 4 F C 4 G D 6 H E, F 7