Question: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2 2 0 0 2 6 0 0 - - - B

Activity Normal time Crash time Normal cost Crash cost Predecessor
A 4322002600---
B 2124002800---
C 33500500---
D 8422002600 A
E 636001200 B
F 3236004200 C
G 4212002000 D,E
What is the total cost of completing this project with the normal completion time.