Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
| Activity | Preceding | Optimistic Time | Probable Time | Pessimistic Time | Expected Time | Variance |
| A | -- | 7 | 9 | 14 |
|
|
| B | A | 2 | 2 | 8 |
|
|
| C | A | 8 | 12 | 16 |
|
|
| D | -- | 3 | 5 | 10 |
|
|
| E | C | 4 | 6 | 8 |
|
|
| F | B | 6 | 8 | 10 |
|
|
| G | F | 2 | 3 | 4 |
|
|
| H | D, E | 2 | 2 | 8 |
|
|
| I | G | 6 | 8 | 16 |
|
|
| J | H | 4 | 6 | 14 |
|
|
| K | I, J | 2 | 2 | 5 |
|
|
Which activities form the critical path?