Question: Activity Predecessor Duration A None 10 B None 14 C None 14 D A,B,C 29 E A,B,C 26 F D,E 51 G F 19 H
| Activity | Predecessor | Duration |
| A | None | 10 |
| B | None | 14 |
| C | None | 14 |
| D | A,B,C | 29 |
| E | A,B,C | 26 |
| F | D,E | 51 |
| G | F | 19 |
| H | F | 19 |
| I | F | 8 |
| J | G,H,I | 4 |
1. Consider a project with 10 activities, which are described in the table below. Given the activity information, draw a network diagram and complete all network calculations using the AON method. Identify the project duration and the critical path.