Question: Activity Predecessor Duration ( days ) A - 2 B A 6 C A 4 D A 2 E B 4 F B , C

Activity Predecessor Duration (days)
A -2
B A 6
C A 4
D A 2
E B 4
F B,C,D 5
G B 3
H E,F 2
Calculate ES, LS, EF, LF show all workings
Calculate Float for each job
What is the project duration?
What is the critical path?
Draw the diagram using the data above.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer To solve this problem well use the Critical Path Method CPM Well calculate the Early Start ES ... View full answer