Question: Activity Predecessor Duration (weeks) a none 4 b none 5 c a, b 8 d c, e 6 e b 2 f e 9 g

Activity Predecessor Duration (weeks)
a none 4
b none 5
c a, b 8
d c, e 6
e b 2
f e 9
g d 7
h f,g 4

Your firm is working on a Sales and Operations improvement project. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. What is the length of the project?