Question: Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while

Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 22. Which of the following is definitely true?

A.

The set of times cannot all be possible.

B.

N is a critical activity.

C.

S is a critical activity.

D.

R has no slack but is not critical.

E.

R is critical and has zero slack.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!