Question: Activity R on a PERT network has predecessors M and N, and has successor S. The duration (t) of R is 5. Late finish (LF)
Activity R on a PERT network has predecessors M and N, and has successor S. The duration (t) of R is 5. Late finish (LF) of N is 18, while late finish (LF) of M is 20. Late start (LS) of S is 14. Which of the following is definitely true?(2 Points)
R is critical and has zero slack
R has no slack but is not critical
S is a critical activity
N is a critical activity
the set of given times cannot all be possible