Question: Activity R on a PERT network has predecessors M and N, and has successor S. The duration (t) of R is 5. Late finish (LF)

Activity R on a PERT network has predecessors M and N, and has successor S. The duration (t) of R is 5. Late finish (LF) of N is 18, while late finish (LF) of M is 20. Late start (LS) of S is 14. Which of the following is definitely true?(2 Points)

R is critical and has zero slack

R has no slack but is not critical

S is a critical activity

N is a critical activity

the set of given times cannot all be possible

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!