Question: Listen Activity R on a CPM network has predecessors M and N , and has successor S . R has duration 5 . N '
Listen
Activity R on a CPM network has predecessors M and N and has successor S R has duration Ns late finish is while Ms is Ss late start is Which of the following is definitely true?
A is critical and has zero slack.
B has no slack but is not critical.
C The set of times cannot all be possible.
D is a critical activity.
E is a critical activity.