Question: Activity Start A B C D E F G H End days 0 2 6 6 9 3 8 3 5 0 a) The Project
| Activity | Start | A | B | C | D | E | F | G | H | End |
| days | 0 | 2 | 6 | 6 | 9 | 3 | 8 | 3 | 5 | 0 |
a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in answer as: ABCD)