Question: Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6

Given is a CPM project network diagram as shown below.

Activity

Start

A

B

C

D

E

F

G

H

End

days

0

2

6

8

3

4

2

3

2

0

a) The Project Completion time = ________ days. b) The Earliest Start time, ES, of Activity G = _______ days. c) The Latest Finish time, LF, of Acitivity C = ______ days. d) The critical activities are = _____ (ex. Fill in answer as: ABCD)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!