Question: Activity time estimates for a production line design & implementation project at Robert Klassen's Ontario factory are as follows: Activity Time (in days) Immediate Predecessors

Activity time estimates for a production line design & implementation project at Robert Klassen's Ontario factory are as follows:

ActivityTime (in days)Immediate Predecessors

A6.0---

B7.2---

C5.0A

D6.0B, C

E4.5B, C

F7.7D

G4.0E, F

  1. Draw an AON network.(3 points)
  2. Perform a forward and backward pass to determine ES, EF, LS, & LF times as well as activity slacks.(11 points)
  3. Identify the total project duration and the critical path.(3 points)
  4. Which approach does this network represent? (Circle one)Explain how you knew for full credit.(3 points)

PERTCPM

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!