Question: Activity time estimates for a production line design & implementation project at Robert Klassen's Ontario factory are as follows: Activity Time (in days) Immediate Predecessors
Activity time estimates for a production line design & implementation project at Robert Klassen's Ontario factory are as follows:
ActivityTime (in days)Immediate Predecessors
A6.0---
B7.2---
C5.0A
D6.0B, C
E4.5B, C
F7.7D
G4.0E, F
- Draw an AON network.(3 points)
- Perform a forward and backward pass to determine ES, EF, LS, & LF times as well as activity slacks.(11 points)
- Identify the total project duration and the critical path.(3 points)
- Which approach does this network represent? (Circle one)Explain how you knew for full credit.(3 points)
PERTCPM