Question: 3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Activity Immediate Predecessors Time (in hours) 6.0

3.7 Task time estimates for a production line

3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Activity Immediate Predecessors Time (in hours) 6.0 7.2 the met- 5.0 6.0 4.5 B, C B.C D EF 7.7 G 4.0 a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length? d) Draw a Gantt chart for the project