Question: Activity Time (in weeks) Immediate Predecessor(s) Activity Time (in weeks) Immediate Predecessor(s) Activity Time (in weeks) Immediate Predecessor(s) A 8 D 8 B G 6

Activity

Time

(in weeks)

Immediate Predecessor(s)

Activity

Time

(in weeks)

Immediate Predecessor(s)

Activity

Time

(in weeks)

Immediate Predecessor(s)

A

8

D

8

B

G

6

E, F

B

6

A

E

10

B

H

6

D

C

3

A

F

5

C

I

4

G, H

This exercise contains only parts b and c.

Part 2

b) The activities on the critical path are

A - C - F - G - I

A - B - D - H - I

A - B - E - G - I

.

Part 3

c) The total project completion time for Howard Corporation is

enter your response here

weeks.

(Enter

your response as a whole

number.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!