Question: Activity Time (in weeks) Immediate Predecessor(s) Activity Time (in weeks) Immediate Predecessor(s) Activity Time (in weeks) Immediate Predecessor(s) A 8 D 8 B G 6
| Activity | Time (in weeks) | Immediate Predecessor(s) | Activity | Time (in weeks) | Immediate Predecessor(s) | Activity | Time (in weeks) | Immediate Predecessor(s) |
| A | 8 | D | 8 | B | G | 6 | E, F | |
| B | 6 | A | E | 10 | B | H | 6 | D |
| C | 3 | A | F | 5 | C | I | 4 | G, H |
This exercise contains only parts b and c.
Part 2
b) The activities on the critical path are
A - C - F - G - I
A - B - D - H - I
A - B - E - G - I
.
Part 3
c) The total project completion time for Howard Corporation is
enter your response here
weeks.
(Enter
your response as a whole
number.)