Question: An activity, A , has two succeeding activities, B and C . Given the following information; determine the latest starting time for activity A .

An activity, A, has two succeeding activities, B and C. Given the following information;
determine the latest starting time for activity A.
EF B =15, EF C =17, LF B =24, LF C =27; activity times are A =4, B =6, C =8.
Select one:
O a.14
O b.
15
c.16
O d.17
e.18