Question: 33. An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B
33. An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =48, LF C = 59; activity times are A = 4, B = 6, C = 8 a. 37 b. 40 c. Insufficient information d. 42 e. 38