Question: 1. An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B
1. An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =51, LF C = 59; activity times are A = 4, B = 6, C = 8
2.
| Season | ||||
| YEAR | SPRING | SUMMER | FALL | WINTER |
| Three years ago | 18 | 10 | 26 | 42 |
| Two years ago | 26 | 18 | 34 | 50 |
| Last year | 34 | 26 | 42 | 58 |
What is the seasonal relative for winter season?