Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,

An activity, A, has two succeeding activities, B

An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =48, LF C = 61, activity times are A = 4, B = 6, C = 8 O a 42 Ob. 38 . 37 Od 40 O e Insufficient information