Question: . Assume that the project is time constrained and try to resolve any overallocation problems by leveling within slack ( see the tutorial video in

.Assume that the project is time constrained and try to resolve any
overallocation problems by leveling within slack (see the tutorial video in MS
Project intro-3). Can you complete the project within 135 days?
Note: No splitting of activities is allowed?
Note: No partial assignments (e.g.,50 percent). All resources must be assigned 100
percent.
4. Assume the project is resource constrained and resolve any overallocation
problems by leveling outside of slack. How long will the project take? When is
the project completion date?.Assume that the project is time constrained and try to resolve any
overallocation problems by leveling within slack (see the tutorial video in MS
Project intro-3). Can you complete the project within 135 days?
Note: No splitting of activities is allowed?
Note: No partial assignments (e.g.,50 percent). All resources must be assigned 100
percent.
4. Assume the project is resource constrained and resolve any overallocation
problems by leveling outside of slack. How long will the project take? When is
the project completion date?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!