Question: Bookbinders project Activity pred time es ef ls lf slack A - 2 0 2 0 2 0 B A 6 2 8 2 8
-
Bookbinders project
Activity
pred
time
es
ef
ls
lf
slack
A
"-"
2
0
2
0
2
0
B
A
6
2
8
2
8
0
C
A
4
2
6
3
7
1
D
C
3
6
9
7
10
1
E
B
2
8
10
8
10
0
F
E,D
8
10
18
10
18
0
G
F
5
18
23
18
23
0
H
A
4
2
6
8
12
6
I
H
10
6
16
12
22
J
I
3
K
G
2
Question 8
What is the Slack of Activity K?
0
5
2
6
3