Calculate early start schedule, late finish, late start and slack Identify critical path(s). Where does the assumption
Question:
Calculate early start schedule, late finish, late start and slack
Identify critical path(s).
Where does the assumption of certainty enter into this model? What is the impact of elements being variable?
Activity | Duration | Predecessors |
1 Select vendor | 1 week | None |
2 Hire Finance module consultant | 4 weeks | 1 |
3 Hire Materials Mgmt consultant | 4 weeks | 1 |
4 Develop internal team | 10 weeks | None |
5 Select hardware system | 3 weeks | 2,3 |
6 Implement hardware system | 8 weeks | 5 |
7 Develop Finance interfaces | 8 weeks | 6 |
8 Install Finance module | 3 weeks | 6 |
9 Test Finance module | 2 weeks | 7,8 |
10 Put Finance module on-line | 0 | 9 |
11 Develop Materials Mgmt interfaces | 15 weeks | 6 |
12 Install Materials Mgmt module | 6 weeks | 10,11 |
13 Test Materials Mgmt module | 3 weeks | 12 |
14 Put Materials Mgmt module on-line | 0 | 13 |
15 Develop Finance user training | 5 weeks | 4,7 |
16 Develop Materials Mgmt user training | 7 weeks | 4,11 |
Please show formulas so that I can learn how to calculate LS and slack.