Question: Conider the project schedule shown in the table below. Activity Predecessor(s) Duration 1 EF 1 3 LS 0 Slack 0 . 0 C . B

Conider the project schedule shown in the table below. Activity Predecessor(s) Duration 1 EF 1 3 LS 0 Slack 0 . 0 C . B D 9 E B, C 4 1 7 1 4 1 7 F 7 G E, F 7 11 7 T What is the slack time for activity C? O A. 3 OB. O OC. 2 OD. 1