Question: Conider the project schedule shown in the table below. Activity Predecessor(s) Duration 1 EF 1 3 LS 0 Slack 0 . 0 C . B

 Conider the project schedule shown in the table below. Activity Predecessor(s)

Conider the project schedule shown in the table below. Activity Predecessor(s) Duration 1 EF 1 3 LS 0 Slack 0 . 0 C . B D 9 E B, C 4 1 7 1 4 1 7 F 7 G E, F 7 11 7 T What is the slack time for activity C? O A. 3 OB. O OC. 2 OD. 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!