Question: Consider a construction project with the following data on precedence relationships, durations, and costs: Activity Immediate predeccessor (s) Normal Time (days) Normal Cost ($) Crash

Consider a construction project with the following data on precedence relationships, durations, and costs:

Activity Immediate predeccessor (s) Normal Time (days) Normal Cost ($) Crash Time (Days) Crash Cost ($)
A - 6 120 4 170
B - 4 120 2 220
C A 3 195 2 270
D A 4 320 2 520
E B, C 7 700 4 1075
F D, E 5 650 2 1100
G E 10 1600 6 2300

F and G are the terminal activities of the project.

(a) Find the critical path.

(b) Find the project completion time and the corresponding cost.

(c) Suppose it is required to complete the project in 22 days. Find which activities to crash and by how much, to yield the minimum project cost.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!