Question: Consider a task: Pessimistic duration is 10 days, Most likely duration is 8 days, Optimistic duration is 5 days, What is the expected duration and

Consider a task: Pessimistic duration is 10 days, Most likely duration is 8 days, Optimistic duration is 5 days, What is the expected duration and the standard deviation of this task? The probability that this task can be completed within 9 days?