Question: Consider the following information about a small project: Task A B D E Duration Estimates 3 days 2 days 2 days 1 day 4 days

Consider the following information about a smallConsider the following information about a small

Consider the following information about a small project: Task A B D E Duration Estimates 3 days 2 days 2 days 1 day 4 days 13 days Immediate Predecessors None A B A B & D E & C b-2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "O" wherever required.) Task Immediate Predecessors None Earliest Start (ES) Earliest Completion (EC) A B A B D E B, D C, E F Task Latest Completion Latest Start (LS) Immediate Successors None Slack F E F. D E C F B CE A B, D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!