Question: Please Help, I will thumbs up. Thank you! Consider the following information about a small project: Task B D E Duration Estimates 2 days 3
Please Help, I will thumbs up. Thank you!
Consider the following information about a small project: Task B D E Duration Estimates 2 days 3 days 3 days 4 days 1 day 9 days TI MOO Immediate Predecessors None A B A B & D E & C m U0 DU0D ? pictureClick here for the Excel Data File b-1. Identify the critical path. O A-D-E-F O A-B-E-F O A-B-C-F b-2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start (ES) Earliest Completion (EC) A Immediate Predecessors None 6 B D mm A BD F Task Latest Completion Latest Start (LS) Slack F Immediate Successors None F E wo D B F B A A BD