Question: Consider the following information about a small project: Task Duration Estimates Immediate Predecessors A 4 days None B 5 days A C 2 days B
Consider the following information about a small project:
| Task | Duration Estimates | Immediate Predecessors | |
| A | 4 | days | None |
| B | 5 | days | A |
| C | 2 | days | B |
| D | 2 | days | A |
| E | 1 | day | B & D |
| F | 10 | days | E & C |
|
| |||
b-2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.)
|
|