Question: Consider the following information about a small project: Task Duration Estimates Immediate Predecessors A 4 days None B 5 days A C 2 days B

Consider the following information about a small project:

Task Duration Estimates Immediate Predecessors
A 4 days None
B 5 days A
C 2 days B
D 2 days A
E 1 day B & D
F 10 days E & C

b-2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.)

Task Immediate Predecessors Earliest Start (ES) Earliest Completion (EC)
A None
B A
C B
D A
E B, D
F C, E
Task Immediate Successors Latest Completion Latest Start (LS) Slack
F None
E F
D E
C F
B C, E
A B, D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!