Question: Consider the following information about a small project: Task Duration Estimates ImmediatePredecessors A 3 days None B 3 days A C 4 days B D
Consider the following information about a small project:
| Task | Duration Estimates | ImmediatePredecessors | |
| A | 3 | days | None |
| B | 3 | days | A |
| C | 4 | days | B |
| D | 2 | days | A |
| E | 2 | days | B & D |
| F | 9 | days | E & C |
|
| |||
a. Identify the critical path.
-
A-B-C-F
-
A-D-E-F
-
A-B-E-F
b. In the first table, identify the early start and early finish for each task. The table header of "Earliest completion" is the same as early finish. (Leave no cells blank - be certain to enter "0" wherever required.)
In this table, identify the late start, late finish, and slack for each task. Note that the task order is now in backward-pass order. Also note the table header of "Latest completion" is the same as late finish. As a reminder, Slack = LF - EF, or can also be calculated as LS - ES. (Leave no cells blank - be certain to enter "0" wherever required.)