Consider the following information about a small project:
| Task | Duration Estimates | Immediate Predecessors | |
| A | 4 | days | None |
| B | 6 | days | A |
| C | 1 | day | B |
| D | 5 | days | A |
| E | 3 | days | B & D |
| F | 9 | days | E & C |
|
| |||
b-1. Identify the critical path.
multiple choice
-
A-B-E-F
-
A-D-E-F
-
A-B-C-F