Question: consider the following work breakdow structure: activity node node optimisitc most likely pessimistic a 1 2 1 1 2 0 2 9 b 2 3

consider the following work breakdow structure:
activity node node optimisitc most likely pessimistic
a 12112029
b 23258
c 24183042
d 3471013
e 14314043
what is the estimated slack time for activity E?
a.0 weeks
b.3 weeks
c.9 weeks
d.11 weeks
e 12 weeks