Question: Consider the following work breakdown structure: Activity A B D Start Node 1 1 2 3 Finish Node 2 3 Optimistic 41 54 58 32

Consider the following work breakdown structure:
Consider the following work breakdown structure:
Consider the following work breakdown structure: Activity A B D Start Node 1 1 2 3 Finish Node 2 3 Optimistic 41 54 58 32 Duration (days) Most Likely 50 60 70 41 Pessimistic 59 66 82 44 4 4 What is the probability that this project will be completed within 130 days? Multiple Choice O .9544 .8413 O 9987 .9772 190