Question: QUESTION 38 Consider the following work breakdown structure: Activity A B Start Node 1 1 2 2 3 4 5 6 Finish Node 2 3

QUESTION 38 Consider the following work breakdown
QUESTION 38 Consider the following work breakdown structure: Activity A B Start Node 1 1 2 2 3 4 5 6 Finish Node 2 3 4 5 5 6 6 7 Duration Estimate (Days) Optimistic Most Likely Pessimistic 9 15 21 13 21 23 6 9 18 23 35 47 19 26 23 29 41 14 20 26 2 5 8 27 D E F G H What is the estimated expected (mean) time (in weeks) for project completion? 35 O 75 O 115 O 170