Question: consider the following work breakdown structure Activity Start Node Finish Node Optimistic Duration (days) Pessimistic A 1 2 41 50 59 B 1 3 54

consider the following work breakdown structure

Activity Start Node Finish Node Optimistic Duration (days) Pessimistic
A 1 2 41 50 59
B 1 3 54 60 66
C 2 4 58 70 82
D 3 4 32 41 44

what is the estimated standard deviation in the time for activity D?

a. 2 days

b. 12 days

c. 0 days

d. 4 days

e. 3 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!