Question: consider the following work breakdown structure Activity Start Node Finish Node Optimistic Duration (days) Pessimistic A 1 2 41 50 59 B 1 3 54
consider the following work breakdown structure
| Activity | Start Node | Finish Node | Optimistic | Duration (days) | Pessimistic |
| A | 1 | 2 | 41 | 50 | 59 |
| B | 1 | 3 | 54 | 60 | 66 |
| C | 2 | 4 | 58 | 70 | 82 |
| D | 3 | 4 | 32 | 41 | 44 |
what is the estimated standard deviation in the time for activity D?
a. 2 days
b. 12 days
c. 0 days
d. 4 days
e. 3 days