Question: Consider the following work breakdown structure: Duration (days) Preceding Task Activity A Optimistic 41 54 DUO Most Likely 50 60 7e 41 Pessimistic 59 66

Consider the following work breakdown structure:
Consider the following work breakdown structure: Duration (days) Preceding Task Activity A Optimistic 41 54 DUO Most Likely 50 60 7e 41 Pessimistic 59 66 82 44 B 00N What is the estimated slack time for activity D? Multiple Choice O days 19 days 20 days 79 days 80 days