Question: Consider the following work breakdown structure for a project: Activity Start Node Finish Node Optimistic Time Most Likely Time Pessimistic Time A 1 2 31

Consider the following work breakdown structure for a project:

Activity Start Node Finish Node Optimistic Time Most Likely Time Pessimistic Time
A 1 2 31 40 49
B 1 3 44 50 56
C 2 4 48 60 72
D 3 4 42 31 34

What is the probability that this project will be completed within 120 days?