Question: Consider the following work breakdown structure for a project: Activity Start Node Finish Node Optimistic Time Most Likely Time Pessimistic Time A 1 2 31
Consider the following work breakdown structure for a project:
| Activity | Start Node | Finish Node | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | 1 | 2 | 31 | 40 | 49 |
| B | 1 | 3 | 44 | 50 | 56 |
| C | 2 | 4 | 48 | 60 | 72 |
| D | 3 | 4 | 42 | 31 | 34 |
What is the probability that this project will be completed within 120 days?