Question: Consider the following work breakdown structure: Start Finish Duration ( days ) table [ [ Activity , Node,Node,Opt nistic , Most Likely,Pessimistic ] ,

Consider the following work breakdown structure:
Start Finish Duration (days)
\table[[Activity,Node,Node,Optnistic,Most Likely,Pessimistic],[A,1,2,41,50,59],[B,1,3,54,60,66],[C,2,4,58,70,82],[D,3,4,32,41,44]]
What is the estimated standard deviation in the time for activity D?
4 days
3 days
O days
12 days
2 days