Question: Consider the following work breakdown structure:ActivityStart NodeFinish NodeTime Estimates ( wks ) totmtpA 1 2 1 1 2 0 2 9 B 2 3 2

Consider the following work breakdown structure:ActivityStart NodeFinish NodeTime Estimates (wks)totmtpA12112029B23258C24183042D3471013E14314043What is the estimated expected (mean) time for activity E?