Question: Cost and schedule data for a small project are given below. Assume an indirect cost of SR 300/day. Activity Depends on A B D E

Cost and schedule data for a small project are

Cost and schedule data for a small project are given below. Assume an indirect cost of SR 300/day. Activity Depends on A B D E A A A B, C&D Cost (SR) Crash Normal 4000 3000 2000 1200 1800 1000 2000 1200 1600 1600 Time (days) Crash Normal 4 5 2 6 4 5 3 3 | | Cost and schedule data for a small project are given below. Assume an indirect cost of SR 300/day. Activity Depends on A B D E A A A B, C&D Cost (SR) Crash Normal 4000 3000 2000 1200 1800 1000 2000 1200 1600 1600 Time (days) Crash Normal 4 5 2 6 4 5 3 3 | |