Question: Critical Path? Slack Time? These are input data for CPM analysis: Activities Predecessors Time in weeks A 5 B A 7 A 3 D B.C

Critical Path?
Slack Time?
Critical Path? Slack Time? These are input data
These are input data for CPM analysis: Activities Predecessors Time in weeks A 5 B A 7 A 3 D B.C 4 E B.C 6 D.E 10 Identify its Critical Path and available slack times for all activities