Question: These are input data for CPM analysis: Activities Predecessors Time in weeks A 07 B 7 A 3 D B,C 4 E E B,C 6

These are input data for CPM analysis: Activities
These are input data for CPM analysis: Activities Predecessors Time in weeks A 07 B 7 A 3 D B,C 4 E E B,C 6 F DE 10 Identify its Critical Path and available slack times for all activities. Your answer may look like: Critical Path is - ABCF Slack times: B-2; C-3