Question: These are input data for CPM analysis: Activities Predecessors Time in weeks A - 5 B A 7 C A 3 D B,C 4 E
These are input data for CPM analysis:
| Activities | Predecessors | Time in weeks |
| A | - | 5 |
| B | A | 7 |
| C | A | 3 |
| D | B,C | 4 |
| E | B,C | 6 |
| F | D,E | 10 |
Identify its Critical Path and available slack times for all activities.