Question: These are input data for CPM analysis: Activities Predecessors Time in weeks A - 5 B A 7 C A 8 D B,C 9 E

These are input data for CPM analysis:

Activities

Predecessors

Time in weeks

A

-

5

B

A

7

C

A

8

D

B,C

9

E

B

2

F

D,E

10

Identify its Critical Path and available slack times for all activities. Provide as Word or Excel file a full CPM diagram with ES, EF, LS, LF numbers as it is described in the video.

Your answer may look like:

Sketch of diagram,

Critical Path is - ABEF,

Slack times: C - 4; D - 3

EXCEL STATS... i know its pretty tedious. would appreciate the help