Question: CyClon Project 2 3 . The CyClon project team has started gathering the information necessary to develop a project network - predecessor activities and activity

CyClon Project
23. The CyClon project team has started gathering the information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in the following table.
\table[[Activity,Description,Duration,Predecessor],[1,CyClon Project,,],[2,Design,10,],[3,Procure prototype parts,10,2],[4,Fabricate parts,8,2],[5,Assemble prototype,4,3,4],[6,Laboratory test,7,5],[7,Field test,10,6],[8,Adjust design,6,7],[9,Order stock components,10,8],[10,Order custom components,15,8],[11,Assemble test production unit,10,9,10],[12,Test unit,5,11],[13,Document results,3,12]]
Part A. Create a network based on the information in the table. How long will the project take? What is the critical path?
Part B. Upon further review the team recognize that they missed three finish-to-start lags. Procure prototype parts will involve only 2 days of work but it will take 8 days for the parts to be delivered. Likewise, Order stock components will take 2 days of work and 8 days for delivery and Order custom components will take 2 days of work and 13 days for delivery.
Reconfigure the CyClon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule? On the amount of work required to complete the project?
Part C. Management is still not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finish-tostart relationships and that it might be possible to reduce project duration by creating start-to-start lags. After much deliberation the team concluded that the following relationships could be converted into start-to-start lags:
Procure prototype parts could start 6 days after the start of Design.
Fabricate parts could start 9 days after the start of Design.
Laboratory test could begin 1 day after the start of Assemble prototype.
Field test could start 5 days after the start of Laboratory test.
Adjust design could begin 7 days after the start of Field test.
Order stock and Order custom components could begin 5 days after Adjust design.
Test unit could begin 9 days after the start of Assemble test production unit.
Document results could start 3 days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine start-to-start lags. What impact did these lags have on the original schedule (Part A)? How long will the project take? Is there a change in the critical path? Is there a change in the sensitivity of the network? Why would management like this solution?
 CyClon Project 23. The CyClon project team has started gathering the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!